Cover Story

Angry Taraba Commissioner, Mrs. Sinjen Insists Tortured 13-year-old girl Must Get Justice

  The  Taraba State Commissioner of Women Affairs and Child Development Mrs. Mary  Sinjen   has condemned the  heinous act committed against...

Work Minister Angry, Threatens To Sack Contractor Handling Jalingo – Numan Road



 The Minister for State, Works and Housing, Engr. Muazu Sambo Jaji says the sum of N3 billion has been approved by the Federal Government to fund the construction of the Numan-Jalingo Road, while warned the contractor handling the work to wake up to the expectations of completing the road or get sacked.

The Jalingo- Numan road which has become a death trap and den of terrorists and armed bandits, was awarded in March 2017 at the cost of N11 billion, to be completed in July 2019.

The Minister during an inspection of Federal roads under construction within Taraba and Adamawa States said the fund would be released to the contractor handling the project in July, adding that it would go a long way towards the execution of the project.

 The Minister, who also visited the site of the construction company, (DEUX Construction Nigeria Limited) located at Numan town in Adamawa State, to ascertain the capability of the company to deliver on the contract, urged the contractor not to leave any stone unturned in delivering quality work.

He admonished the contractor to be more serious when the funds are released in the next few days or loose the contract to a more competent construction company.

When asked on the rationale behind the delay in executing the project, the company site engineer, Frank Kohshola, confessed that only the sum of N1.5 Billion was given to the company after the award of the contract since 2017.

Kohshola also linked the setback witnessed by the project to paucity of fund, said the total amount of money earmarked for the job was not released to the company.

 

Aside the paucity of fund, the contractor also highlighted insecurity in the area, noting that the two challenges have hampered their operation.

 

The engineer supervising the work from Federal Ministry of Works and Housing, Yola Field Office, Maria Zira, said the company had submitted two certificates of non rejection, but payment was still pending.

 

She also identified insecurity as one of the factors that has been militating against the execution of the work.

 

 


No comments