AN OPEN LETTER OF COMPLAINT AND REQUEST FOR THE SETTING UP OF A FACT-FINDING COMMITTEE TO INVESTIGATE THE AWARD AND THE PURPOTED EXECUTION OF PROJECTS ACROSS TARABA STATE BY THE NORTH-EAST DEVELOPMENT COMMISSION IN THE SUM OF N26,845,194,966.03 (TWENTY-SIXBILLION, EIGHT HUNDRED AND FORTY-FIVE MILLION, ONE HUNDRED AND NINETY-FOUR THOUSAND, NINE HUNDRED AND SIXTY-SIX NAIRA,POINT THREE KOBO)


 

AN OPEN LETTER OF COMPLAINT AND REQUEST FOR THE SETTING UP OF A FACT-FINDING COMMITTEE TO INVESTIGATE THE AWARD AND THE PURPOTED EXECUTION OF PROJECTS ACROSS TARABA STATE BY THE NORTH-EAST DEVELOPMENT COMMISSION IN THE SUM OF N26,845,194,966.03 (TWENTY-SIXBILLION, EIGHT HUNDRED AND FORTY-FIVE MILLION, ONE HUNDRED AND NINETY-FOUR THOUSAND, NINE HUNDRED AND SIXTY-SIX NAIRA,POINT THREE KOBO)  

1. We are a firm of Legal Consultants, Solicitors, Advocates, Human Right Activist, Members of the Amnesty International, Aspirant Members of the World Jurist Association with our office name and address above and below the first page of this letter.
2. Sir, we write as patriotic citizens of Taraba Stateto appreciate you and your indefatigable members of the Executive, Legislative and Judicial arms of the Government for the patriotic discharge of the onerous responsibility of the Government of Taraba State. May the Almighty God continue to bless the State, the leaders and the entire citizens of the State.
3. As concerned citizens, we owe you and the State a duty of providing necessary information whenever same is received which may use for the benefit of the State. 
4. Your Excellency Sir, the Federal Government, during the tenure of late President Muhammadu Buhari, through the North-East Development Commission budgeted the above-mentioned sum of money for the below listed projects; thus  

 

 

 

 

 

PROJECT

SUM

LOCATIONS

REMARK

 

 

1

Construction of 160 Mass Housing Units in Jalingo, Taraba State

N776,327,289.60

Jalingo

Ongoing as at 2022

 

 

 

 

 

 

2

2 Blocks of class rooms for Primary Schools in Baisa, Kurmi

N410,703,022.12

Baisa, Kurmi 

Ongoing as at 2022  

 

 

 

 

 

3

2 blocks of classrooms for Primary School in Jalingo

N410,703,022.12

Jalingo

Ongoing 

as at 

2022

 

 

 

 

 

 

4

2 blocks of classrooms for Primary School, Wukari

N410,703,022.12

Wukari

Ongoing as at 2022

 

 

 

 

 

5

2 blocks of classrooms for Secodary School, Jalingo

N403,597,427.99

Jalingo

Ongoing as at 2022

 

6

 

2 blocks of classrooms for Secondary School, Baissa

N403,597,427.99

Baissa, Kurmi

Ongoing as at 2022

 

 

 

7

2 blocks of classrooms for Secondary School, Wukari 

N403,597,427.99

Wukari 

Ongoing as at 2022

 

8

340 mass housing units spread across other LGAs in the State including Wukari, Zing, Bali, Takum and Sardauna 

N1,649,695,490.00

Takum/Sardauna

Ongoing as at 2022

 

9

Construction of additional structures to stabilize Mayo Ndaga bridge (Phase II)

N95,224,250.00

Sardauna 

Ongoing as at 2022

 

10

Construction of administrative blocks, Staff quarters and other buildings in Baissa, Kurmi 

N284,946,184.15

Baissa, Kurmi

Ongoing as at 2022

 

11

Construction of administrative blocks, Staff quarters and other buildings in Jalingo

N284,946,184.15

Jalingo

Ongoing as at 2022

 

12

Construction of administrative blocks, Staff quarters and other buildings in Wukari 

N284,946,184.15

Wukari 

Ongoing as at 2022

 

13

Construction of Birama Primary School, KashimbillaTakum

N800,027,832.64

Takum

Ongoing as at 2022

 

14

Construction of input stores, toilet, security post, nursery shed and perimeter chain-link fencing six (6) nursery sites in Taraba State

N35,1000,000,00

Taraba 

Ongoing as at 2022

 

15

Construction of Lau to Karim-Lamido road

6,210,000,000.00

Lau/Karim-Lamido

Ongoing as at 2022

 

16

Construction of Rural Roads and Drainage Infrastructure in Taraba State 

N500,000,000.00

Taraba 

Ongoing as at 2022

 

17

Construction of single span Mayo Ndaga Bridge (Phase I)

N106,908,070.56

Sardauna 

Ongoing as at 2022

 

18

Construction Virology Lab (Bio-Safety Level 2) in Federal Medical Centre Jalingo

N95,570,017.88

Jalingo

Ongoing as at 2022

 

19

Drilling handpump borehole in communities, rehabilitation of health centres in communities and supply of classroom desks in Ussa LGA

N49,802,741.60

Ussa  

Ongoing as at 2022

 

20

Drilling handpump borehole in communities, renovation and supply of classroom desks and Rehabilitation of health centres in communities 

N49,994,020.93

Takum

Ongoing as at 2022

 

21

Drilling handpump borehole/solar borehole and rehabilitation of health centres in communities  

N49,984,084.75

Zing 

Ongoing as at 2022

 

22

Drilling handpump borehole/solar borehole, supply of drugs and medical disposables and renovation and supply of classroom desks in Karim Lamido 

N49,958,855.60

Karim Lamido

Ongoing as at 2022

 

23

Drilling handpump borehole/solar borehole, supply of drugs and medical disposables and renovation and supply of classroom desks in Yorro 

N49,973,463.66

Yorro 

Ongoing as at 2022

 

24

Drilling handpump borehole/solar borehole, supply of drugs, medical disposables and equipment 

N49,452,731.66

Ardo-Kola 

Ongoing as at 2022

 

25

Drilling of handpumps, rehabilitation of health centres and supply of drugs, medical disposables and equipment, Gashaka

N49,985,712.23

Gashaka

Ongoing as at 2022

 

26

Drilling of handpumps, rehabilitation of health centres and supply of drugs, medical disposables and equipment as well as Renovation and supply of classroom desks, Bali

N49,941,133.44

Bali 

Ongoing as at 2022

 

27

Drilling of handpumps, rehabilitation of health centres and supply of drugs, medical disposables and equipment as well as Renovation and supply of classroom desks, Donga

N49,618,402,09

Donga 

Ongoing as at 2022

 

28 

Drilling of handpumps, rehabilitation of health centres and supply of drugs, medical disposables and equipment as well as Renovation and supply of classroom desks, Gassol

N49,902,422.23

Gassol

Ongoing as at 2022

 

29

Establishment of 3 new Forestry Nurseries with General Silvicultural services through: Drilling of solar-powered boreholes, reticulation of water supply, chain-link fencing of borehole areas in each of the Nurseries in Taraba State 

N49,950,000.00

Taraba 

Ongoing as at 2022

 

30

Establishment of 40-bed rehabilitation centres in Taraba State 

N284,480,939.00

Taraba 

Ongoing as at 2022

 

31

Establishment of ICT Training Centre at Federal University, Wukari 

N45,000,000.00

Wukari 

Ongoing as at 2022

 

32

Establishment of ICT Training Centre at FedpolyBali

N45,000,000.00

Bali 

Ongoing as at 2022

 

33

Establishment of ICT Training Centre at Taraba State Uni, Jalingo

N45,000,000.00

Jalingo

Ongoing as at 2022

 

34

Establishment of Phase One Forestry Nurseries in the State 

N25,073,366.67

Taraba 

Ongoing as at 2022

 

35

Handpump borehole rehabilitation in communities, Afforestation of 1 hectare in JalingoLGA and Renovation and supply of classroom desks 

N49,997,660.42

Jalingo

Ongoing as at 2022

 

36

Procurement of Fertilizers and non-fertilizer agrochemicals for Pilot distribution to farmers in the state 

N67,179,000.00

Taraba 

Ongoing as at 2022

 

37

Procurement of mechanization and Primary Processing equipment for establishment of Agricultural mechanization/primary processing services in the 3 Senatorial districts of the State 

N290,898,268.46

Taraba 

Ongoing as at 2022

 

38

Procurement of Nursery tools and equipment for seedling production and other nursery and plantation activities in Taraba State 

N44,199,500.00

Taraba 

Ongoing as at 2022

 

39

Procurement of processing equipment for establishment of rice milling and oil processing plants in the 3 senatorial districts of the State

N94,273,431.91

Taraba 

Ongoing as at 2022

 

40

Procurement of Rice and Maize seed for Pilot distribution to farmers in the state

N21,000,000.00

Taraba 

Ongoing as at 2022

 

41

Profiling Studies for the control of land degradation in GTB States 

N16,666,666,67

Taraba 

Ongoing as at 2022

 

42

Rehabilitation of health centres in communities and the supply of drugs, medical disposables and equipment 

N49,511,027.06

Ibi 

Ongoing as at 2022

 

43

Rehabilitation of Jalingo-MararrabanApawa-Yola Road

N10,960,000,000.00

Taraba 

Ongoing as at 2022

 

44

Renovation and supply of classroom desks and rehabilitation of health centre in communities 

N49,991,990.89

Wukari 

Ongoing as at 2022

 

45

Renovation and supply of classroom desks and rehabilitation of health centres in communities 

N49,941,797.58

Lau 

Ongoing as at 2022

 

46

Solar borehole rehabilitation in communities, rehabilitation of health centres in communities and renovation and supply of classroom desks 

N49,853,573.01

Kurmi 

Ongoing as at 2022

 

47

Solar borehole rehabilitation in communities, rehabilitation of health centres in communities and renovation and supply of classroom desks in communities 

N49,996,829.31

Sardauna 

Ongoing as at 2022

 

48

Solar powered lighting system electrification of the Federal Science and Technical College Jalingo, Taraba State 

N99,162,743.10

Jalingo

Ongoing as at 2022

 

49

Statutory environmental studies for the NEDC projects in Taraba State 

N20,000,000.00

Taraba 

Ongoing as at 2022

 

50

Supply and installation of 5 sets of complete solar system (10KVA) with Hybrid inverter, deep cycle gel batteries, controllers, 320 watts solar panels and a fire truck with all accessories in Federal Polytechnic Bali, Taraba State. 

N93,020,000.00

Bali 

Ongoing as at 2022

 

51

Three batches of ICT Training (N@200 trainees/batch) 

N129,000,000.00

Taraba 

Ongoing as at 2022

 

52

Training and empowerment of 5 persons on fabrication of energy efficient stove and briquette production (for Artisans, TOT)

N20,508,750.00

Taraba 

Ongoing as at 2022

 

53

Training of 100 youths as trainers on various aspects of waste collection and management, training of 200 waste dump scavengers, procurement of 500 PPEs and the establishment of an efficient Waste Collection and Management system, including procurement, installation and operationalization of a Plastic Recycling Plant in Taraba State 

N84,350,000.00

Taraba 

Ongoing as at 2022

 

54

Training workshop on climate change awareness and adaptation, including alternative energy and energy efficiency in Taraba State 

N45,933,000.00

Taraba 

Ongoing as at 2022

 

 

 

5. Your Excellency sir, 80% of the above-mentionedprojects were not carried out as investigations from the affected areas reveals.
6. Your excellency sir, as a concerned citizen of the State, who love to see progress rather than backwardness of the State as we learnt from you, we deem it desideratum to appeal to your exalted office under your distinguished and exemplary leadership to set up a powerful Fact-Finding Committee to go round the 16 Local Government Areas where the projects are said  to have been executed with the view to finding out the reality or otherwise of the projects.
7. Sir, the people of the State are appreciative of the way and manner you are piloting the affairs of the State and pray for God guidance and protection for you to continue with your beneficial projects and securing the lives and properties of the citizens of the State.  
8. Your Excellency Sir, if our complaint ismeritorious, and the Government is inclined to setting up the Fact-Finding Committee, we urge your exalted office to have regards to the representation by the Nigerian Bar Association, Jalingo and Wukari Branches for effective Fact-Finding and Report delivery.

 

Please have the assurances of our unquantifiable support and solidarity for your administration.

 

NB: We wrote this letter as an open complaint to avoid incidences of diversion of same to avoid reaching your exalted table. 

 

Yours In Private Legal Practice, 

 

 

Isa Buba, Esq.